How to calculate days of cover from a feedstock stockpile

Days of cover is the number procurement teams actually want when they look at a supplier's pile: not "how big is it" but "how long does that pile last at the rate they're burning through it." The math is simple once you have two inputs. Getting those two inputs right is where most buyers go wrong.
The basic math
Days of cover = current stockpile volume (converted to tonnes) divided by average daily consumption.
So if a coking coal pad holds 40,000 tonnes and the plant draws 2,000 tonnes a day, that's 20 days of cover. Nothing complicated about the division. The work is in the two numbers you're dividing.
Volume is usually the easier half, and it's still not trivial. A pile measured by eye from the roadside, or estimated off a supplier's own stock report, carries enough error that "40,000 tonnes" could really be 34,000 or 46,000. Conical and ridge piles don't hold volume the way people assume, and a pile that's been reclaimed from one side looks bigger from the road than it is. If you're converting a volume reading into tonnes, you need a bulk density figure for that specific material, not a generic number pulled from a textbook. Iron ore fines, lump ore, thermal coal and clinker all pack differently, and moisture content shifts the number further.
Daily consumption is the half people guess at. A plant's nameplate capacity is not its draw rate. Nameplate tells you what the line can process running flat out; the real draw rate reflects maintenance windows, blend changes, and whatever the plant is doing that quarter. The honest way to get a daily consumption figure is to watch the pile shrink over several weeks and back-calculate the run rate from the draw-down, rather than taking the supplier's stated throughput at face value.
Why a single reading isn't enough
One volume reading gives you a snapshot, and a snapshot alone can't tell you a draw rate. Twenty days of cover sounds fine until you realize that number came from a single measurement paired with a guessed consumption figure. The pile could have been building for two months before that reading, or drawing down fast right before it.
What tells you something is a sequence: this week's volume against last week's, and the week before that. Once you have three or four consecutive readings, the slope between them is your real daily draw rate, not someone's estimate of it. Divide the latest volume by that slope and the days-of-cover figure stops being a guess and starts being a trend line you can act on.
This is also how you catch a shortage before the supplier tells you about one. A pile that's flat for six weeks and then starts dropping 3% a week isn't sending you a memo. It's just getting smaller, reading after reading, and the days-of-cover number falls with it. By the time a supplier admits to a feedstock gap, the pile has usually been shrinking for a month.
Setting a buffer, not just a number
Days of cover on its own doesn't tell you whether to act. You need a threshold: the point at which a falling number triggers a call to the supplier, a second sourcing option, or a change in your own production schedule. That threshold depends on your lead time to replace the material, not on some industry-standard figure, since lead time varies by commodity and by how far the supplier's feedstock has to travel.
A reasonable approach is to set the buffer at your replacement lead time plus a margin for the supplier missing their own schedule, which they will, eventually. If it takes four weeks to arrange an alternate ore shipment, you don't want your days-of-cover number crossing four weeks before you've already started making calls.
Getting a reliable days-of-cover figure depends on having a volume reading you trust and enough of them in sequence to calculate a real draw rate rather than assume one. A weekly pile reading at the named supplier site gives you that sequence without waiting on whatever the supplier chooses to report and whenever they choose to send it.